Estimation of the formworks’ quantity
In constructional works, it is common practice to pay the technicians responsible for the form- work implementation, based upon the quantity (in m3) of casted concrete. However, the most proper way is to separate those two things therefore, the following pages regard the estimation of the required moulds.
Ground floor
Beams – Slabs |
m2 |
||
S1: |
3,80 x 5,00 – 4 x 0,40 x 0,10 + 2 x 3,60 x 0,18 |
= |
20,136 |
b1,b2: |
2 x 5,00 x 0,50 + 2 x (5,00-2 x 0,40) x 0,32 + + 2 x 4,20 x 0.30 |
= |
10,208 |
columns (joints): |
4 x 0,40 x 0,50 + 4 x 0,40 x 0,32 + 4 x 0,10 x 0,32 |
= |
1,440 |
Sum |
= |
31,784 |
|
Columns: |
|||
4 x (0,40 x 0,40 x 2,50) |
= |
16,000 |
Basement
Beams – Slabs |
m2 |
||
S1: |
4,50 x 3,90 – 4 x (0,15 x 0,15) |
= |
17,460 |
b1,b2: |
2 x [5,00 x 0,50 +4,20 x 0,32] + 4,20 x 0,25 |
= |
9,788 |
b3: |
4,40 x 0,50 + 3,60 x 0,32 + 3,60 x 0,25 |
= |
4,252 |
sw5: |
4,40 x 0,50 + 3,60 x 0,32 |
= |
3,352 |
internal column sides |
4 x 2 x 0,15 x 0,32) |
= |
0,384 |
Sum |
= |
35,236 |
Columns: |
4 x (0,40 x 0,40 x 2,50) – 2 x (0,25 x 2,50) |
= |
14,750 |
Shear wall sw5: |
2 x (3,60 x 2,50) |
= |
18,000 |
Sum |
= |
32,750 |
Foundation
m2 |
|||
Footings F3,4,5: |
0,50 x [5,00 + 2 x 1,00 + 0,30 x 2] |
= |
5,85 |
Cb1,2: |
2 x [0,70 x0,10 + 4,30 x 0,60 + 0,30 x 0,30] 2 x [0,30 x0,10 + 3,60 x 0,60 + 0,30 x 0,30] |
= |
10,04 |
Sf4: |
(3,80 + 4,40) x 0,30 + (3,60 + 4,40) x 0,30 |
= |
4,86 |
Columns: |
2 x 2 [0,10 x 0,30 +0,10 x 0,10] + +(4,40+3,60 ) x 0,10 |
= |
0,96 |
Sum |
= |
21,71 |