In constructional works, it is common practice to pay the technicians responsible for the form- work implementation, based upon the quantity (in m3) of casted concrete. However, the most proper way is to separate those two things therefore, the following pages regard the estimation of the required moulds.

Ground floor


Beams – Slabs

m2

S1:

3,80 x 5,00 – 4 x 0,40 x 0,10 + 2 x 3,60 x 0,18

=

20,136

b1,b2:

2 x 5,00 x 0,50 + 2 x (5,00-2 x 0,40) x 0,32 +

+ 2 x 4,20 x 0.30

=

10,208

columns (joints):

4 x 0,40 x 0,50 + 4 x 0,40 x 0,32 + 4 x 0,10 x 0,32

=

1,440

 

Sum

=

31,784

Columns:

 
 

4 x (0,40 x 0,40 x 2,50)

=

16,000

Basement


Beams – Slabs

m2

S1:

4,50 x 3,90 – 4 x (0,15 x 0,15)

=

17,460

b1,b2:

2 x [5,00 x 0,50 +4,20 x 0,32] + 4,20 x 0,25

=

9,788

b3:

4,40 x 0,50 + 3,60 x 0,32 + 3,60 x 0,25

=

4,252

sw5:

4,40 x 0,50 + 3,60 x 0,32

=

3,352

internal column

sides

4 x 2 x 0,15 x 0,32)

=

0,384

 

Sum

=

35,236

Columns:

4 x (0,40 x 0,40 x 2,50) – 2 x (0,25 x 2,50)

=

14,750

Shear wall sw5:

2 x (3,60 x 2,50)

=

18,000

 

Sum

=

32,750

Foundation


 

m2

Footings F3,4,5:

0,50 x [5,00 + 2 x 1,00 + 0,30 x 2]

=

5,85

Cb1,2:

2 x [0,70 x0,10 + 4,30 x 0,60 + 0,30 x 0,30]

2 x [0,30 x0,10 + 3,60 x 0,60 + 0,30 x 0,30]

=

10,04

Sf4:

(3,80 + 4,40) x 0,30 + (3,60 + 4,40) x 0,30

=

4,86

Columns:

2    x    2    [0,10    x    0,30    +0,10    x    0,10]    +

+(4,40+3,60 ) x 0,10

=

0,96

 

Sum

=

21,71


 