Structural System – II

Structural System – II

Estimation

Bar Bending Schedule

Bar Bending Schedule

Serial # Bar Designation Number

of Bars

Length

of one

Bar

Dia of bar

Weight of Steel Required

Shape of

Bar

#10 #13 #15 #19 #25

1

M-1

#25

2

S-1

#10

3

H-1

#15

Total weight of steel = 1.05Σ , 5% increase, for wastage during cutting and bending

Bar Bending Schedule (contd…) 


Additional Length = 0.414 h

Total Length = L + 0.414h

2h = 1.414h

1.414h – 1h = 0.414 h



Bar Bending Schedule (contd…)



Bar Bending Schedule (contd…)

M-1 = 4000 + 2 x 228 – 2 x 40 + 2 x (18 x 20)

5096

h = 375 – 2 x 40 – 2 x 10 – 2 (15/2) = 260

M-2 = 4000 + 2 x 228 – 2 x 40 + (0.414 x 260) x 2

5091

H-1 = 4000 + 2 x 228 – 2 x 40

4376

Bar Bending Schedule (contd…)

Shear stirrups


Number of Bars = 4000 /180 +1 = 24

a = 375 – 2 x 40 – 10 = 285 mm

b = 228– 2 x 40 – 10 =138 mm b

Total length of S-1 = 2 (138 + 285 + (4×10 + 75)) = 1076 mm

Bar Bending Schedule


Concluded